You are here:HOME > PRODUCTS > Rice Mill Plant > 300 Ton Rice Mill Production Line: VMTCP-300 Specifications
300 Ton Rice Mill Production Line: VMTCP-300 Specifications
This 300T/D rice mill plant is a large customized rice processing plant that can get 8-9ton final rice from paddy rice. It contains a paddy cleaner, rice de-stoner, rice huller, paddy separator, rice mill machine, rice polisher, rice color sorter, rice packing machine, etc.
Quick answer: The VOSON VMTCP-300 is presented as a 300 ton-per-day automatic rice mill production line based on 24-hour operation, with a published power range of 400-1200 kW. Its stated process covers paddy cleaning, destoning, husking, paddy separation, whitening, polishing, grading, color sorting, conveying and packing. The final proposal must convert these planning values into an agreed capacity basis, equipment list, utility schedule and acceptance test.
VMTCP-300 rice mill production line. Equipment quantity and arrangement must be confirmed against the paddy, finished-rice target, building and operating schedule.
VMTCP-300 published specifications
Planning item
Published VMTCP-300 value
Contract point to confirm
Nominal capacity
300 tons per day over 24 hours
Whether the figure means paddy input, finished-rice output or another basis.
Arithmetic hourly average
12.5 tons per hour when 300 tons are divided evenly across 24 hours
Required design margin for maintenance, changeover and actual plant utilization.
Published power range
400-1200 kW
Final connected load, simultaneous running load, voltage, transformer and generator duty.
Process boundary
Paddy intake through finished-rice packing
Machine quantities, elevators, bins, platforms, dust control, air system and automation.
Control
PLC-controlled automatic line
Control architecture, interlocks, alarms, manual modes and local support.
Structure
Steel-frame or building-supported arrangement
Site layout, foundation loads, access, weather and local construction rules.
Capacity note: The 12.5 t/h figure is transparent arithmetic, not a separate throughput guarantee. The contract should state paddy condition, operating hours, test duration, allowed downtime and whether performance is measured at intake or finished-rice discharge.
300 TPD rice milling process and equipment
The published sequence is raw-paddy feeding, cleaning and destoning, husking, paddy separation, rice milling, polishing, grading, color sorting and packing. A complete line performs only as well as its slowest stage, so every quoted machine should show model, quantity, rated capacity and motor power.
Bag range, weighing accuracy, speed, sewing, vacuum packing and palletizing scope.
Define the 300 TPD capacity basis
Daily capacity alone is not enough for equipment selection. Specify paddy variety, moisture, impurity level, storage condition and seasonal variation. Then define finished-rice recovery, whiteness, polishing level, broken-rice limits, grading fractions, accepted color defects and packing sizes.
Operating time also changes the design. A plant expected to produce 300 tons in 20 effective hours needs a higher hourly rate than one operating continuously for 24 hours. Planned cleaning, screen changes, roll replacement and product changeover should be included when setting the line margin.
Power, air, water and dust collection
The published 400-1200 kW range is a preliminary envelope. Request a motor schedule for all process machines, conveyors, elevators, fans, compressors, color sorters, packers and auxiliaries. The electrical engineer should distinguish total connected power from the expected simultaneous demand.
Confirm site voltage and frequency, transformer sizing, distribution panels, cable boundary, power-factor correction and backup-power requirements. Color sorters and pneumatic machines need clean, stable compressed air. Mist polishing may require controlled water supply, while cleaners, elevators and whitening equipment need adequate aspiration and dust collection.
Layout, structure and maintenance access
The VMTCP-300 can be configured on a steel support structure or coordinated with a building. Before civil work starts, obtain a dimensioned layout with equipment elevations, pits, openings, foundation loads, service platforms and maintenance clearances.
Allow safe access for replacing rubber rolls, screens, motors, bearings and larger components. The responsibility matrix should identify who supplies bins, platforms, stairs, handrails, ducts, electrical panels, local wiring, lighting and fire protection. Local structural and safety codes remain part of the project design.
Automation, staffing and commissioning
PLC control can coordinate feeding, machine interlocks, alarms and shutdown logic, but it does not remove the need for trained staff. The whole factory still needs intake control, laboratory testing, packing, warehouse work, maintenance, utilities, cleaning and supervision.
Commissioning should include dry checks, no-load rotation, interlock tests, loaded adjustment and a defined performance run. Training should cover routine operation, quality adjustments, cleaning, safety, preventive maintenance and fault response. Record the paddy condition and every agreed result during the trial.
Quotation and acceptance checklist
Quotation evidence
Minimum content
Decision supported
Process flow diagram
Every machine, bypass, return stream and storage point
Whether the configuration can produce the required rice grades.
Equipment schedule
Model, quantity, rated capacity, motor and material-contact parts
Technical comparison between suppliers on the same basis.
Layout and load plan
Dimensions, elevations, access, pits, openings and foundation loads
Building feasibility, installation sequence and maintenance access.
Utility schedule
Power, air, water, ventilation and dust collection
Transformer, compressor and infrastructure planning.
Commercial boundary
Freight, unloading, erection, wiring, training and spare parts
Complete project budget and responsibility allocation.
Acceptance protocol
Input basis, duration, throughput, recovery, quality and downtime
Use the rice mill project cost checklist to budget machinery, building, utilities, freight and startup. The Rice Mill Project Planning Hub organizes the wider purchasing workflow. For a configuration, send paddy data, finished-rice targets, operating hours, packing, voltage, site country and building limits through Contact.
300 ton rice mill production line FAQ
What is the published capacity of the VMTCP-300?
The published basis is 300 tons per day over 24 hours. The quotation should state whether this means paddy input or finished-rice output.
What is the hourly capacity of a 300 TPD rice mill?
Dividing 300 tons by 24 hours gives 12.5 tons per hour. Actual equipment selection needs margin for the operating schedule, paddy condition and downtime.
How much power does the VMTCP-300 require?
The published planning range is 400-1200 kW. The final electrical design must use the approved equipment and simultaneous-load schedule.
Does the line include color sorting and packing?
The published process includes color sorting and packing. The number of sorters, packing format, bag range and automation boundary must be stated in the quotation.
Can the plant use a steel structure?
Yes. A steel-frame or building-supported layout can be prepared, subject to site dimensions, local structural rules and maintenance access.
What should a performance test record?
Record paddy condition, input rate, finished output, milling recovery, broken rice, quality grades, power demand, test duration and downtime.